Tuesday, 6 August 2013

Mass concrete works have been completed to the retaining wall and the facing stonework has been laid ready for coping stones.

Kerbing and hard landscaping works are progressing to the front of Block 1 and adjacent to Block 2.

Friday, 21 June 2013

Excavations ,steel fixing and concrete pour for the retaining wall are now completed. The gas trench is now excavated and gas, water and electric are now connected to all plots.






Monday, 22 April 2013

Works have progressed steadily on site and we have managed to strip the majority of our scaffold on our 2 single blocks and complete the render to reveal the buildings.

Block 1

The Stonework is nearing completion and our scaffold is due to be taken down on the front early next week to allow excavation of service trenches. Next week should also see the return of our Ground Workers to start completing the externals, by shaping the road, laying kerbs and flagging around plots.

Block 2 with scaffold stripped and render complete


Internally we are skim complete in Blocks 2 & 3, in 4 plots we have started the completion items, we have Mist coated and installed 2nd fix M&E and kitchens are being fitted.


Monday, 8 April 2013

The weather has finally improved and has enabled us to make good progress on site. The roof is complete and works have started on the external stone work and we are already at the 1st fix stage upstairs.


The stone work on Blocks 2 & 3 has been completed and we have partially stripped the scaffold, leaving enough to allow the renderers to work off. Internally we have completed our 1st fix in all 4 plots and have closed up and skimmed in Block 2.


Next week should see the Dryliners complete the perimeter boarding and internal walls leaving the plots ready for the follow on trades who are all lined up and ready to go.


Friday, 15 March 2013

Block 1

This week has been very productive with our roofers working through the wind of the first few days to get the felt and battens on and load the tiles out for laying. A couple of weeks will see the roof complete. This will leave our Plumber to fit the Gutters and Rain Water Pipes.


Blocks 2 & 3

The external stone work is up past first floor, and the internal walls have been erected ready for First Fixing the M&E.


Next week will see an increase in activity with internal works starting on Block 1 and First Fix kicking off in Blocks 2 & 3.

Friday, 8 March 2013

Block 1

The Timber Kit has been erected ready for the roof to start which is schedule for Monday. Windows will follow on hopefully making the buildings water tight in a few weeks.

Block 2 and Block 3

Roof on, windows in and the external stone work up to first floor, internal plaster boarding has been started and the acoustic floor has been laid.
  
Next week will see an increase in the workforce on site to get Block 1 Roofed and start internal stud walls to get the plots ready for 1st Fix M&E.